Business Services » Measure V

Measure V

Fillmore Unified School District
 Measure V Bond Summary
June 30, 2022
       
  Project Expenditures  
       Expended to 6/30/2022 
    Piru  
    Security Upgrades  $                5,236
    VoIP/Communications Upgrade   $              20,331
       
    San Cayetano  
    Courtyard Improvements  $            319,731
    Classroom Modernization:  Carpet Installation  $            167,271
    Campus-Wide Painting  $            289,597
    Shade Structure  $              49,711
    Security Upgrades  $                5,236
    VoIP/Communications Upgrade   $              26,146
       
    Rio Vista  
    Shade Structure   $              71,378
    Security Upgrades  $              15,605
    VoIP/Communications Upgrade   $              20,331
       
    Mountain Vista  
    Campus-Wide Painting  $              87,832
    Roof Repair / Replacement  $            823,655
    Security Upgrades  $                5,236
    VoIP/Communications Upgrade   $              26,146
       
    Sierra High School  
    Shade Structure / Solar Lights  $              99,253
    Security Upgrades  $              22,673
    VoIP/Communications Upgrade   $              20,331
       
    Fillmore Middle School  
    New Junior Varsity Baseball Field Complex  / Walking Path  $    1,781,413
    Campus-Wide Painting  $            142,745
    Fire Alarm Upgrades  $            425,535
    Security Upgrades  $                5,236
    VoIP/Communications Upgrade   $              49,731
       
    Fillmore High School  
    CTE Classrooms (Systems Diagnostics, Service and Repair; Agriculture)   $      13,189,819
    Athletic Complex  $            105,310
    Upgrade Electrical  $         2,388,487
    Roof Repair - West Wing  $            744,480
    Window Replacement - Science Building  $            446,257
    Gym Improvement - Doors, Windows  $            210,907
    Security Upgrades  $              14,939
    Classroom Modernization  $            827,887
    Cafeteria  $              94,622
    Library  $            507,261
    VoIP/Communications Upgrade   $              24,789
       
    School Farm  
    Flexible Space / Modular Buildings & New Boys' and Girls' Modular Restroom Building  $            283,739
    Flexible Space / Restrooms  $            218,118
       
    District Wide  
    Bond Project Consultant  $              72,669
    Data Center  $                4,740
    VoIP/Communications Upgrade   $              40,756
       
    Total Expenditures  $      23,655,137